A Parrish Punchlist: What Work Remains?

Feb 15, 2012 11:28 AM

A Parrish Punch list:

What Work Remains?

• Install insulation

• Complete duct work, geothermal HVAC system and plumbing

• Complete electrical work

• Finish installing glass, including the glass cafe curtain wall

• Finish the interior walls, including placing plywood beneath the sheetrock for stable art-hanging surfaces and millwork

• Stucco the northern exterior gallery entrance

• Furnish the interior, including benches in the cafe and custom-made light finishes in the multipurpose room

• Furnish the cafe and terrace with a “Parrish chair” by Munich-based industrial designer Konstantine Grcic

• Finish interior and exterior doors

• Place final sealant on the floors

• Do tile work and install fixtures in restrooms and custodial closets

• Cover all four sides of the roof with white corrugated metal

• Transfer the permanent collection and operations from current museum

• Landscape the grounds, including leveling and grading

• Complete fire-access road with reinforced pavers

• Widening of Montauk Highway